Lead and lag concept
There are three tasks A, B, and C. A has duration fo 5 weeks. B cannot start until A has ended and 1 extra week has been used to assign team memebers. C starts one week after B starts. When does event C end, if B = 6 weeks duration and C = 8 weeks duration? What is the depency between B & C above?
Source: Farndale's PMP
Answer: at th end of ...... weeks; and ....... to .......
Other than just to answer, more analysis are below, comment if anything you feel different/ incorrect.
1. There is 1 week lag between taks A and B; and dependency is start to finish