Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

huge cost variance

 Hi,

 

You have huge cost variance in your project from milestone to milestone. 

Which of the following will not be an action you will take?

1. you will rebase line the project

2. you will do variance analysis

3. you will report cost variance to sponsor on regular basis and corrective actions you plan to take