risk mgt question

Ted, a team member, is assigned as a risk owner.  He should also be in ?

a) performing the risk audit

b) determining risk thresholds

c) meeting with senior mgt

d) developing risk response

greatly confused with the answer for this question.

I feel the situation is in planning phase of project. therefore, Performing risk audit is ruled out, determining risk thresholds is generally done at high level and being team member he cannot take a big call on this matter.

It lies in between (c) n (d).