cost management- BAC calculation

 The original cost baseline for a project is $600,000. There is a management reserve of $50,000. The project manager finds it necessary to use $20,000 of the management reserve. The value for Budget at completion, BAC is now:

Answer is given as $620,000

 

Can someone explain the concept?

 