Critical path early start early finish different ways ?
Hello,
I am in my final preparation for PMP.
I have a question regarding critical path in PMP exam.
I have seen on different ressources two ways to calculate early start and early finish.
Some saying that early start = early finish of previous task
Other saying early start = early finish of previous task +1
At the end you have these two results with :
task A 5 days and task B 3 days, B following A
=> If early start = early finish of previous task
task A ES=0 EF =5