Very confusing fixed price contract and risk transfer
Submitted by smartcode on Sun, 12/16/2012 - 17:17
Forums:
In your project, you have been sub-contracting your IT development work to four consultancy firms. Which of the following statements about transferring risk to a contractor is not true?