Verify scope - Question on output

Hi,

I was attempting a question and a question was

Which of the following is not an output of Verify scope

1. Accepted deliverables

2. Project management plan updates

3. Project document updates

 

Obviously the right answer is the 3. But it is very difficult to remember. can some one tell me when there is a project management plan updates and when project document updates?

 

 