Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Question on contract change

66.

After awarding contract to one of the sellers, you realize you have missed a clause for the delay in the contract and want to modify it. how should you proceed further ?

A ) Contract is legally binding and cannot be changed once signed

b ) Project manager should inform the seller about the change in the next meeting

c ) project manager should inform the seller about the change though a formal written communication

d ) project manager should proceed with contract change control system at his end

what do you think it is and why ?

 