PERT on Critical path question
Does anyone know how to calculate the below.
Question:
Together with your team you applied three point estimation on a Critical path containing two activities.
The following duration uncertainities are calculated using +/-3sigma confidence interval.
The duration uncertaining-defined as Pessimistic minus optimistic estimate - of the first activity is 18 days; the second estimate has an uncertainity of 24 days. Applying the PERT formula for paths, what is the duration uncertaining of the entire path?