Free PMP Exam Sample Qstion
Submitted by pmpodcast on Fri, 05/20/2011 - 10:47
Forums:
The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
------------------------------
The method of constructing a project schedule network diagram that represents activities and connects them to show the dependencies is known as:
A) Arrow diagramming method
B) Schedule network templates
C) Precedence diagramming method
D) Activity list