What stance to take when answering PMP exam questions?

A question such as follows:


When negative risk occurs, a response to it is called?


Options include contingency plan and workaround.


Problem is that the question does not specify whether this risk that occurred was anticipated during contingency planning. According to Rita's, you're supposed to assume that proper project management was done if it does not specify otherwise.