PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

NPV Question

 Assume a discount rate of 2% per year and an investment of 100.000€. You expect to receive revenue of 20.000€ in the first year and 45.000€ in the second year. What is the approximate projected Net Present Value (NPV) of your investment at the end of year two?

A. -37.000 €

B. -35.000 €

Pages