EV Question
Submitted by getpmpinct on Tue, 05/11/2010 - 02:16
Forums:
A project management professional can compare earned value performance data to all of the following project
management tools EXCEPT:
A. Critical path analysis.
B. Technical performance metrics.
C. Risk mitigation plans.
D. Forecasted final costs and schedule estimates.
What is the ans. I am not able to understand the question. Can someone help?
Thanks in advance.