EAC value ??

anmol2701's picture

You are a project manager for creating an online mega store. Customers can log in to the online store and order any item ranging from household to luxury items. The project is underway. You accept project costs to date and assume future work (ETC) will be performed at the budgeted rate. If BAC = 700, ETC = 175, PV = 200, AC = 100, EV = 150, and cumulative CPI = 1.5, what is the EAC?

Options are 1) 540        2) 650    3) 500     4) 450

 