Communications Mgmt question

You receive a last minute status report from a senior member of the project team that you believe is incorrect. It shows tasks as complete that you are almost certain are no more than 60% complete, and it documents deliverables as having being turned over to the customer that you do not believe are even finished yet. You are walking into a communication meeting with key stakeholders. What is the BEST way to handle this problem?