Why "Reject Change Requests" is an Input to "Monitor & Control Proj Work Process

Dear PMPs,

 I am studying for the test and as I am looking for ITTOs for each process and trying to understanding the purpose of each one. I found that "Reject Change Requests" is an input to Monitor and Control project work process (Integration). Any idea why we need to feed a rejected change request as input to this process. Please advice.

 Thanks