PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Rita's Conflicting answers

Hi,

   Here are two questions from Rita Mulcahy's book.

1. The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is best thing for the project manager to do?

A. Compress the schedule to recover the two weeks

B. Cut scope to recover the two weeks

C. Consult with the sponsor before taking any action

D. Advise the client of the impact of the change.

 