Question on - Quality Audits
116. A project customer and a contractor agreed on regular quality audits during execution by a third party audit team, which is working on an assignment for the customer. What should the contractor have prepared for the audits?
1 Work results
2 Measurements and test results
3 Quality documentation
4 Contract-related correspondence
Guys,
for this question, the right answer is 3 and I am not too sure what does Quality documentation is required for that.. but here is what I think of the other answer