PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Question on Cost

A project manager is estimating project costs and needs to decide whether the estimates will include only direct costs, or whether the estimates will also include indirect costs. In which of the following phases does this decision need to take place?

A. Define Scope
B. Estimate Costs
C. Plan Expenses
D. Determine Budget

I tought this kind of decision took place in plan cost management ?
anyone can explain as the choice is not there?

thanks

Pages