PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Question on conflict resolution - Scordo

As project manager, you scheduled a status update meeting. During the meeting, a problem developed and the group discussed it. The day after the meeting, Kevin approached you and expressed his concerned that the problem was not really resolved. After thinking about it, he felt that his concerns were still valid and should be addressed. what conflict resolution method was likely used at the status meeting.

A. Smoothing

B. Foircing

C. Withdrawal

D. Collaboration

 