PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Question regarding Net Present Value

Hi All,

Can you please assist me in addressing this sample PMP exam question regarding Net Present Value (i.e. what is the key formula to solving)?

Thank you!
Justin

A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000.

The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.

Pages