Communication Channels Exam Question - Answer doesn't make sense

The answer is 35. But I get 45. Not sure why it's 35.

You are the project manager for the ABC Project. Initially you have identified 5 stakeholders in your project. As the project moved ahead, 5 more stakeholders got involved in the project.

Assuming that they all need to communicate with each other, how many additional communication channels are there?

Choose one answer.
A. 5 Incorrect
B. 45 Incorrect
C. 35 Correct
D. Cannot be evaluated Incorrect
Incorrect
Marks for this submission: 0/1.