Critical Path Question

Activity 1 - Duration 4,starts immediately
Activity 2 - after act 1,Duration 8
Activity 3 - after act 2,Duration 5
Activity 4 - after act 1,Duration 8
Activity 5 - must take place concurrently with activity 3,Duration 3,starts after acts. 4 and 2

What is duration of critical path

18,15,17,12

Can someone show the network diagram for this??