Critical Path Question
Submitted by chullan88 on Tue, 06/17/2014 - 19:33
Forums:
Activity 1 - Duration 4,starts immediately
Activity 2 - after act 1,Duration 8
Activity 3 - after act 2,Duration 5
Activity 4 - after act 1,Duration 8
Activity 5 - must take place concurrently with activity 3,Duration 3,starts after acts. 4 and 2
What is duration of critical path
18,15,17,12
Can someone show the network diagram for this??