PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Contract Question

1) After a lot of negotiations, you awarded the contract to a seller for providing serivices on testing a complex application. Midway through the project the seller approaches you stating that the seller is unable to get the required software resources to complete the project. what is the best thing to do?

A. Terminate the contract as the seller has breached the contract.
B. Discuss with seller and find a solution.
C. Document the concerns
D. Remind the seller that they are contractually obliged to deliver.