PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Two questions

1). A project is considered successful when
A. the product of the project has been manufactured
B. the project sponsor announces the completion of the project
C. the product of the project is turned over to the operations area to handle the ongoing
aspects of the project
D. the project meets or exceeds the expectations of the stakeholders

Answer is D

But when it exceeds expectations doesn't that mean it is gold plating

Pages