If project time and cost are
Submitted by Jp2786 on Tue, 05/27/2014 - 00:12
Forums:
If project time and cost are not as important as the no. of resources used each
month, which of the following is the BEST thing to do?
a) Perform a Monte Carlo analysis
b) Fast track the project
c) Perform resource leveling
d) Analyze the life cycle costs
Views pls