Do PMP Test still use "poorly wording" now?
Submitted by bluesky7804 on Mon, 12/23/2013 - 16:45
Forums:
The correct answer is A (from Velociteach)
Margo is working with her team to evaluate each known unknown and try to assign an estimated percentage probability of occurrence of each. In what process is the team participating?
A. Risk analysis
B. Risk identification
C. Plan responses
D. Control risks