SPI and CPI
Submitted by vraccess on Wed, 12/09/2015 - 00:27
Forums:
I had a below question in Oliver
|
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?92 o The project was terminated early. At that time, it was over budget and ahead of schedule. |