Your subcontractor delivered building raw material 3 days late, To bring some degree of satisfaction he reduced its cost by 5%. This offer is an example of
A. Compromise
B. Collaborate
C. Smoothing
D. Forcing
I selected answer A, but it's saying the answer is B (Collaborate).
Please clarify on this.