Time Management Questions
Question 1
If project itme and cost are not as important as the number of resources used each month, which of the following is the best thing to do?
A. Perform Monte Carlo Analysis
B. Fast tack the project
C. Perform resource leveling
D. Analyze the life cycle costs
Question 2
Which of the following is a benefit of an analogous project estimate.
A. The estimate will be closer to what the work will actually require
B. IT is based on a detailed understanding of what the work requires