Maximum float

 Q: Sponsor wants the project completed in 40 days.

The CPI is 1.1 , the project critical path duration is 38 days with a standard deviation of 2 days. What is the maximum project float?
 
A. 8 days
B. 2 days
C. 4 days
D. 0 days
 
Please point out the correct answer with explanation.