Maximum float
Submitted by ginumon on Thu, 07/18/2013 - 06:39
Forums:
Q: Sponsor wants the project completed in 40 days.
The CPI is 1.1 , the project critical path duration is 38 days with a standard deviation of 2 days. What is the maximum project float?
A. 8 days
B. 2 days
C. 4 days
D. 0 days
Please point out the correct answer with explanation.
