Procedures of two different companies

 You are a new project manager for company B. You have previously worked for company A, which had an extensive project management practice. Company B has its own procedures, but you are more familiar with those from company A. You should:

 

a. interact with others in ethical way in sharing the good aspects of company A's procedures.

b. Use the forms from company B and recommend ways to upgrade them.

c. Talk about changes to change control board of company B.

d. Use the practice from company A but include any forms from company B.