Do we need to update PC if PM changes?

 Hi,

I am not sure, but just would like to confirm from the PMP members do we need to update the Project Charter if a Project Manger is changed ?

My opinion is to update and need to get officially signed to make sure the 2nd Project Manger is approved to execute & continue the project which was handled by the 1st Project Manager.

Please let me know your thoughts.

-KKV