Contact Changes
Submitted by elthox on Thu, 07/04/2013 - 11:38
Forums:
Hi,
From Rita`s Fastrack I picked the following question;
Which of the following is the PRIMARY cause of contract changes?
A) Independent Estimates
B) Organisational policies
C) Procurement Statement of work
D) Change Request