EV Question
Your project team has completed 50% of works for a construction project with a total budget of $ 1,250,000. So far the project has already spent $ 400,000 and is expected to perform with the current rate until the end of the project. What is the correct statement about this project?
a. The project will finish within the schedule
b. The total cost of the project will be $ 1,250,000
c. The project estimated requires $ 400,000 to complete
d. The project sponsor concerns that the project might require to use the management reserves
Question source : Self-made