Earned Value management Question
Submitted by taifii on Fri, 06/28/2013 - 14:13
Forums:
If one Project should complete in 10000 $ and required number of hours 1200 with hourly labour cost 150 per hour.
But In actually they reach the cost 8000$ and number of hours spend 1400 with hourly labour cost 150per hour so what will be Earned Value.