schedule reserve
Submitted by vijayavadrevu on Fri, 06/14/2013 - 14:51
Forums:
A project has a schedule reserve of 28 days when the customer adds scope not previously planned for. The change has a 40% chance of delaying the project by 14 days. What should be done?
A) Look for ways to cut 14days of work from another activity
B)Add 5.6 days to schedule reserve
C)Add more resources to the project
D)Plan to add 14 days of overtime to the project