which process??
Submitted by vijayavadrevu on Tue, 06/04/2013 - 15:38
Forums:
A major construction project has included in the project budget the cost of the construction loans taken out to finance the work, and this will be accounted for on a monthly basis. The project manager will factor in these cost estimates into the project during which process?