plan risk response
Submitted by vijayavadrevu on Mon, 05/20/2013 - 17:49
Forums:
You are developing a risk response plan. However, every time you come up with a risk response plan, another risk is identified caused by the response. What should be your BEST approach?
A)Make a documentation of the new risk events and carry on with the Plan Risk Responses process
B)Try to understand the project work better