risk identification process

 A project review by project office identifies that a particular project team has completed the risk identification process without considering the project network diagram. Which of the following is the most likely outcome under this situation?

A)Schedule risks are missed

B)Resource risks are missed

C)Cost risks are missed

D)Activity convergence risks are missed