WBS changes
Submitted by vijayavadrevu on Sat, 05/18/2013 - 11:12
Forums:
Jack's project has gone through few changes to the WBS elements which was agreed before. The changes have been approved using the appropriate change control process. The WBS changes might result in which of the following? Select the BEST answer.
A)Scope changes
B)Cost changes
C)Schedule revisions