Q related standard deviation
Submitted by Novjot on Sun, 05/12/2013 - 18:01
Forums:
Hi All ,
i have an doubt in a standard deviation related question.
Q: The expected value for your project duration estimate is 627 days, and the most likely duration estimate is 575. The standard deviation is 14. Which of the following statements is true?