PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Work Package Vs Control Accounts

There were two Questions in two differents books , With diffennt Options 

A.  At what level the scope, cost, and schedule are integrated and compared to the earned value for performance measurement.

  1. Control Account Level
  2. Work Package Level
  3. Activity Level

 

B. At what level the scope, cost, and schedule are integrated and compared to the earned value for performance measurement.

  1. Work Package Level
  2. Activity Level