Duration of activity
Submitted by svsatheeshkumar on Wed, 07/10/2013 - 12:36
Forums:
An activity has a ES of 3 days, LS of 13 days, EF of 9 days and LF of 19 days. What is the duration of this activity ?
a) 3
b) 6
c) 7
d) 10
Given Answer : B
What is the correct formula to use ?
Duration = Early Finish - Early Start + 1 (Assuming 1 as start of the day)
= 9 - 3 + 1 = 7
Duration = Early Finish - Early Start (Assuming 0 as start of the day)