Progressive Elaboration and T&M
Submitted by wmclemore on Fri, 06/21/2013 - 12:59
Forums:
OK, Here is my question of the day. Have not been able to find a explaination for this one.
When should a time and material contract with a contractor been chosen instead of a fixed price contract.
Answer:
When project scope includes the progressive elaboration of the scope of deliverables.
Question:
WHY
:-) Thanks