Is Project Scope Statement should be input to Validate scope?
Submitted by gpatha78 on Fri, 08/05/2016 - 03:56
Forums:
Project Scope statement includes Acceptance Criteria : (As per 5.3.3.1 section of PMBOK 5, A set of conditions that is required to be met before deliverables are accepted).
As per 5.5 section of PMBOK 5 - Validate Scope is the process of formalizing acceptance of the completed project deliverables. Project scope statement is not part of Inputs of Validate Scope.