Is Project Scope Statement should be input to Validate scope?

Project Scope statement includes Acceptance Criteria : (As per 5.3.3.1 section of PMBOK 5, A set of conditions that is required to be met before deliverables are accepted). 

As per 5.5 section of PMBOK 5 -  Validate Scope is the process of formalizing acceptance of the completed project deliverables.   Project scope statement is not part of Inputs of Validate Scope.  