Dependency relation query
Submitted by pmpnewster on Tue, 06/11/2013 - 08:12
Forums:
Can someone please clarify the below doubt?
We have two sequential activities A and B (they could be part of a complex PDM network diagram) with some dependency (SS, FF, SF) specified. NO LAGS or LEADS are given.
1. SS relnship: Means that B cannot start until A has started. Fine. BUT does SS relnship also require that B must start at the same time as A, i.e., they start simultaneously?