Early start calculation: Add 1 to early finish or not?

In some sources, early start equals early finish of the previous activity. In other sources, early start is early finish + 1 of previous activity. I know it is a technicality of how you do your project, but which way is correct in the PMP exam? I made mistakes between Rita and Headfirst practice questions because each uses a different method.

Thanks guys.

 