Help with Reserves Questions
Submitted by mlmPMP2013 on Tue, 04/30/2013 - 01:27
Forums:
Hi All --
I believe this question is incorrect:
Jackie is the project manager of large project. During the Determine Budget phase, she identifies that contingency reserves need to be made for unplanned but potentially required changes that could result from realized risks identified in the risk register. Which of the following is true about reserves?
-
Reserves are not a part of project cost baseline, but may be included in the total budget for the project