Resource Calendar Query
Submitted by siddus on Sat, 04/27/2013 - 10:18
Forums:
As per the PMBOK, Resouce Calendars are inputs of the Estimate Activity Resources, Estimate Activity Duration, and Develop Schedule processes. Resource Calendars are obtained from the Acquire Team process in the Execution process group. I am unable to comprehend how one can have access to resource calendars in the planning phase while planning the schedule before the calendars are made available in the execution phase while acquiring the team.